Contract
No: HK/2015/01 Wanchai Development Phase II and Central
Wanchai Bypass Sampling, Field Measurement
and Testing Work (Stage 3) Environmental Permit no. EP-376/2009, Further Environmental Permits No. FEP-01/376/2009
and FEP-02/376/2009 Monthly Environmental
Monitoring & Audit Report
- January 2017 -
|
CLIENTS: |
|
Civil Engineering and Development Department |
Lam Geotechnics Limited 11/F Centre
Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
February 2017 |
2.2 Scope of the Project and Site Description
2.3 Project Organization and Contact Personnel
3 status of regulatory compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
5.2 Air Quality Monitoring Results
6.3 Review of the Reasons for and the Implications of
Non-compliance
6.4 Summary of action taken in the event of and follow-up
on non-compliance
7 Cumulative Construction Impacts due to the
Concurrent Projects
9 Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule 2
Designated Projects under this Project
Table 2.2 Contact
Details of Key Personnel
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2012/08
Table 3.3 Summary of submission status under
FEP-01/376/2009 Condition
Table 4.1 Noise
Monitoring Stations
Table 4.2 Air Quality
Monitoring Stations
Table 5.1 Noise
Monitoring Stations for Contract no. HK/2012/08
Table 5.2 Air Quality
Monitoring Station for Contract no. HK/2012/08
Table 5.3 Details of Waste Disposal for Contract no.
HK/2012/08
Table 8.1 Summary of Environmental
Inspections for Contract no. HK/2012/08
Table 9.1 Cumulative
Statistics on Complaints
Table 9.2 Cumulative
Statistics on Successful Prosecutions
LIST OF FIGURES
Figure 2.1 Project Layout
Figure 2.2 Project
Organization Chart
Figure 4.1 Locations of
Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental
Mitigation Implementation Schedule
Appendix 4.1 Action and Limit
Level
Appendix 4.2 Copies of
Calibration Certificates
Appendix 5.1 Monitoring
Schedule for Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical
Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical
Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification of Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme
of Individual Contracts
Contract no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan
Chai Bypass at Wan Chai West
·
Drainage
Noise Monitoring
Air Quality Monitoring
Complaints, Notifications of Summons and Successful Prosecutions
Site Inspections and Audit
Future Key Issues
Contract no. HK/2012/08
– Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West
·
Drainage
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed
take up the role as the Environmental Team (ET) under Environmental Permit no.
EP-376/2009 and Further Environmental Permits no. FEP-01/376/2009 and
FEP-02/376/2009 to implement the Environmental Monitoring and Audit (EM&A)
programme as stipulated in the EM&A Manual of the approved Environmental
Impact Assessment (EIA) Report for Wan Chai Development Phase II and
Central-Wan Chai Bypass (Register No.: AEIAR-458/2008).
1.1.2.
This report documents
the finding of EM&A works for Environmental
Permit (EP) no. EP-376/2009 and Further Environmental Permits no.
FEP-01/376/2009 and FEP-02/376/2009, during the period of 27th December 2016 to 26th January 2017. The cut-off date of reporting is the 26th of each reporting
month.
Section 1 Introduction – details the scope and structure of the
report.
Section 2 Project
Background – summarizes
background and scope of the project, site description, project organization and
contact details of key personnel during the reporting period.
Section 3 Status of
Regulatory Compliance – summarizes the status of valid Environmental Permits / Licenses
during the reporting period.
Section 4 Monitoring
Requirements – summarizes
all monitoring parameters, monitoring methodology and equipment, monitoring
locations, monitoring frequency, criteria and respective event and action plan
and monitoring programmes.
Section 5 Monitoring
Results – summarizes
the monitoring results obtained in the reporting period.
Section 6 Compliance Audit – summarizes the auditing of monitoring results, all exceedances
environmental parameters.
Section 7 Cumulative
Construction Impact due to the Concurrent Projects – summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Environmental Site
Audit – summarizes
the findings of weekly site inspections undertaken within the reporting period,
with a review of any relevant
follow-up actions within the
reporting period.
Section 9 Complaints,
Notification of summons and Prosecution – summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 10 Conclusion
2.1.1
Wan Chai Development
phase II and Central-Wan Chai Bypass (hereafter called “the Project”) are
Designated Project (DP) under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The Environmental Impact Assessment (EIA) Report for Wan
Chai Development phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-125/2008) has been approved on 11 December 2008.
2.2.1.
The design and
construction of Wan Chai Development Phase II and Central Wanchai Bypass
involves the construction and operation of primary and district distributor
roads that is shown at Figure 2.1.
2.2.2.
The key purpose of
the study area
encompasses the Wan Chai harbourfront area. The area starts at the boundary of
Central Reclamation Phase III (CRIII) at the west and connects to the existing
Hung Hing Road at the east. The scope of the project includes:
·
A dual 2-lane primary distributor road, Road
P2, approximately 0.6km in length; and
·
Other new primary and district distributor
roads connecting to the slip roads of the Central-Wan Chai Bypass with a total
length of approximately 0.7km.
2.2.3.
The project also contains various Schedule 2 DP
that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table
2.1 summarises the DP under this Project. Figure 2.1 shows the locations of these Schedule 2 DP.
Table 2.1 Schedule 2 Designated Project under this Project
Item |
Designated Project |
EIAO Reference |
DP2 |
Road P2 and other roads which are
classified as primary/district distributor roads |
Schedule 2, Part I, A.1 |
2.2.4.
The designated
project work II (DP2) was awarded to China State-Leader Joint Venture
HK/2012/08 (Contract Title: Wan Chai Development Phase II Central – Wan Chai
Bypass at Wan Chai West) as part of the Project works by the Civil Engineering
and Development Department (CEDD). The construction work under Contract no. HK/2012/08 was commenced on 13 May
2015.
2.3.1
Civil Engineering and Development Department and
Highway Department are the overall project controllers for the Wan Chai Development
Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project,
Project Engineer, Contractor(s), Environmental Team and Independent
Environmental Checker are appointed to manage and control environmental issues.
2.3.2
The proposed project organization and lines of
communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact
particulars are summarized in Table 2.2:
Table 2.2 Contact
Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3922 3388 |
3912 3010 |
|
China State- Build King Joint Venture |
Contractor under Contract no. HK/2012/08 |
Project Director |
C. N. LAI |
9106 5806 |
2877 1522 |
Project Manager |
Mr. Eddie Chung |
9189 8118 |
|||
Site Agent |
Mr. Keith Tse |
9037 1839 |
|||
Environmental Officer |
Mr. James Ma |
9130 9549 |
|||
Environmental Supervisor |
Mr. Y. L. HO |
9856 5669 |
|||
Ramboll Environ Hong Kong Limited |
Independent Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader
(ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.3.3
In this reporting month, the principal work
activities of the contract is included as follows:
Contract no. HK/2012/08
– Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West
·
Drainage
2.3.4
In coming reporting month, the principal work
activities of the contract is anticipated as follows:
Contract no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan
Chai Bypass at Wan Chai West
·
Drainage
3.1.1.
A summary of the current status on licences
and/or permits on environmental protection pertinent to the Project is shown in
Table 3.1.
Table 3.1 Summary of the current status on licences and/or permits on
environmental protection pertinent to the Project
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-376/2009 |
13 Nov 2009 |
Valid |
Further
Environmental Permit |
FEP-01/376/2009 |
31 Mar 2015 |
Valid |
Further
Environmental Permit |
FEP-02/376/2009 |
1 Aug 2016 |
Valid |
3.1.2.
The current status on licences and/or permits on
environmental protection pertinent for contract no. HK/2012/08 under FEP-02/376/2009
showed in Table 3.2. and Table 3.3
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2012/08
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-01/376/2009 |
31 Mar 2015 |
N/A |
Valid |
|
FEP-02/376/2009 |
1 Aug 2016 |
N/A |
Valid |
Notification of Works Under APCO |
355439 |
4 Feb 2013 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
5213-134-C3790-01 |
30 Jun 2016 |
N/A |
Valid |
Billing Account under Waste Disposal
Ordinance |
7016883 |
18 Feb 2013 |
18 Jul 2017 |
Valid |
Water Discharge
Licence |
WT00018470-2014 |
6 Mar 2014 |
31 Mar 2019 |
Valid |
Construction Noise
Permit |
GW-RS0746-16 |
12 Jul 2016 |
14 Jul 2016 to
12 Jan 2017 |
Expired |
|
GW-RS0736-16 |
12 Jul 2016 |
14 Jul 2016 to
12 Jan 2017 |
Expired |
|
GW-RS1332-16 |
29 Dec 2016 |
13 Jan 2017 to 12 Jul 2017 |
Valid |
|
GW-RS1340-16 |
23 Dec 2016 |
13 Jan 2017 to 12 Jul 2017 |
Valid |
Table 3.3 Summary of submission status under FEP-01/376/2009 Condition
EP
Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management Plan (Rev. 2) |
Generally in order as
commented by EPD on 27 Oct 2015 |
Condition 2.10 |
Landscape Plan (Rev. 0) |
Generally in order as
commented by EPD on 5 Aug 2015 |
3.1.3.
Implementation status of the recommended
mitigation measures during this reporting month is presented in Appendix 3.1.
NOISE Monitoring Station
4.1.1.
The noise monitoring station for the Project is
listed and shown in Table 4.1 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.1 Noise Monitoring
Station
District |
Station |
Description |
Wan Chai |
M1a |
Harbour Road
Sports Centre |
Noise Monitoring Parameters, Frequency and Duration
4.1.2.
The construction
noise level shall be measured in terms of the A-weighted equivalent continuous
sound pressure level (Leq). Leq (30 minutes) shall be
used as the monitoring parameter for the time period between 0700 and 1900
hours on normal weekdays. For all other time periods, Leq (5 minutes)
shall be employed for comparison with the Noise Control Ordinance (NCO)
criteria. Supplementary information for data auditing,
statistical results such as L10 and L90 shall also be obtained for reference.
4.1.3.
Noise monitoring shall be carried out at all
the designated monitoring stations. The monitoring frequency shall depend on
the scale of the construction activities. The following is an initial guide on
the regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
·
One set of measurements between 0700 and 1900
hours on normal weekdays.
Monitoring Equipment
4.1.4. As referred to in the Technical Memorandum ™ issued under the NCO, sound
level meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agrees to within 1.0 dB.
4.1.5. Noise measurements shall not be made in fog, rain, wind with a steady
speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall
be checked with a portable wind speed meter capable of measuring the wind speed
in m/s.
Air Quality Monitoring Stations
4.2.1. The air quality monitoring stations for the Project are listed and shown
in Table 4.2 and Figure 4.1. Appendix 4.1 shows the
established Action/Limit Levels for the monitoring works.
Table 4.2 Air Quality Monitoring
Stations
Station ID |
Description |
CMA5b |
Pedestrian
Plaza |
CMA6a |
WDII PRE Site
Office |
Air QUALITY Monitoring Parameters, Frequency and Duration
4.2.2. One-hour and 24-hour TSP levels should be measured to indicate the
impacts of construction dust on air quality. The 24-hour TSP levels shall be
measured by following the standard high volume sampling method as set out in
the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix
B.
4.2.3. All relevant data including temperature, pressure, weather conditions,
elapsed-time meter reading for the start and stop of the sampler,
identification and weight of the filter paper, and any other local atmospheric
factors affecting or affected by site conditions, etc., shall be recorded down
in detail.
4.2.4. For regular impact monitoring, the sampling frequency of at least once
in every six-days, shall be strictly observed at all the monitoring stations
for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency
of at least three times in every six-days should be undertaken when the highest
dust impact occurs.
Sampling Procedure and Monitoring Equipment
4.2.5. High volume samplers (HVSs) in compliance with the following
specifications shall be used for carrying out the 1-hour and 24-hour TSP
monitoring:
·
0.6 – 1.7 m3 per minute adjustable
flow range;
·
Equipped with a timing / control device with
+/- 5 minutes accuracy for 24 hours operation;
·
Installed with elapsed-time meter with +/- 2
minutes accuracy for 24 hours operation;
·
Capable of providing a minimum exposed area
of 406 cm2;
·
Flow control accuracy: +/- 2.5% deviation
over 24-hour sampling period;
·
Equipped with a shelter to protect the filter
and sampler;
·
Incorporated with an electronic mass flow
rate controller or other equivalent devices;
·
Equipped with a flow recorder for continuous
monitoring;
·
Provided with a peaked roof inlet;
·
Incorporated with a manometer;
·
Able to hold and seal the filter paper to the
sampler housing at horizontal position;
·
Easily changeable filter; and
·
Capable of operating continuously for a
24-hour period.
4.2.6. Initial calibration of dust monitoring equipment shall be conducted upon
installation and thereafter at bi-monthly intervals. The transfer standard
shall be traceable to the internationally recognized primary standard and be
calibrated annually. The concern parties such as IEC shall properly document
the calibration data for future reference. All the data should be converted into
standard temperature and pressure condition.
Laboratory Measurement / Analysis
4.2.7. A clean laboratory with constant temperature and humidity control, and
equipped with necessary measuring and conditioning instruments to handle the
dust samples collected, shall be available for sample analysis, and equipment
calibration and maintenance. The laboratory should be HOKLAS accredited.
4.2.8. Filter paper of size 8” x 10” shall be labelled before sampling. It
shall be a clean filter paper with no pinholes, and shall be conditioned in a
humidity-controlled chamber for over 24-hours and be pre-weighed before use for
the sampling.
4.2.9. After sampling, the filter paper loaded with dust shall be kept in a
clean and tightly sealed plastic bag. The filter paper shall then be returned
to the laboratory for reconditioning in the humidity controlled chamber
followed by accurate weighing by an electronic balance with readout down to 0.1
mg. The balance shall be regularly calibrated against a traceable standard.
4.2.10. All the collected samples shall be kept in a good condition for 6 months
before disposal.
4.2.11. Current calibration certificates of equipment are presented in Appendix 4.2.
5.0.1. The environmental monitoring will be implemented based on the division
of works areas of the designated project managed under the contract with FEP
applied by individual contractors.
Overall layout showing work areas of various contracts, latest status of
work commencement and monitoring stations is shown in Figure 2.1 and Figure 4.1. The monitoring results are presented in according to the Individual
Contract(s).
5.0.2. In the reporting month, the concurrent contract is:
Contract no. HK/2012/08 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai West.
5.0.3. The environment monitoring schedules for reporting month and coming
month are presented in Appendix 5.1.
5.1.1
The proposed division of noise monitoring
station is summarized in Table 5.1 below.
Table 5.1 Noise
Monitoring Station for Contract no. HK/2012/08
Location ID |
District |
Description |
M1a |
Wan Chai |
Harbour Road Sports Centre |
5.1.2
No action or limit level exceedance was
recorded in this reporting month.
5.1.3
The noise monitoring results measured in this
reporting period are reviewed and summarized. Details of the noise monitoring
results and graphical presentation can be referred to Appendix 5.2.
5.2.1 The proposed division of air quality monitoring stations are summarized
in Table 5.2 below.
Table 5.2 Air Quality Monitoring Station for Contract no. HK/2012/08
Station |
Description |
CMA5b |
Pedestrian Plaza |
CMA6a |
WDII PRE Site Office |
5.2.2 One 24hr TSP action level exceedance was recorded at CMA5b on 20 January
2017.
5.2.3
No construction works
under EP-376/2009 was undertaken on 20 January 2017 around Pedestrian Plaza
under Contract HK/2012/08, no particular observation regarding air quality
impact was observed during sampling. In view of the above, the action level
exceedance was considered to be non-project related and potentially contributed
by local ambient condition such as road traffic next to the monitoring station.
5.2.4
The air quality
monitoring results measured in this reporting period are reviewed and
summarized. Details of air quality
monitoring results and graphical presentation can be referred in Appendix 5.3.
5.3.1 No Inert and non-inert C&D wastes disposed in this reporting month.
Details of the waste flow table are summarized in Table 5.3.
Table 5.3 Details of
Waste Disposal for Contract no. HK/2012/08
Waste Type |
Quantity this
month |
Cumulative Quantity-to-Date |
Disposal /
Dumping Grounds |
Inert C&D materials
disposed, m3 |
NIL |
NIL |
NIL |
Inert C&D materials
recycled, m3 |
NIL |
NIL |
NIL |
Non-inert C&D materials
disposed, m3 |
NIL |
NIL |
NIL |
Non-inert C&D materials
recycled, m3 |
NIL |
NIL |
NIL |
Chemical waste
disposed, kg |
NIL |
NIL |
NIL |
6.0.1. The Event Action Plan for construction noise and air quality are
presented in Appendix 6.1.
6.1.1 No
action or limit level exceedance was recorded in this reporting month.
6.1.1. One 24hr TSP action level exceedance was recorded at CMA5b on 20 January
2017.
6.1.2.
No construction works
under EP-376/2009 was undertaken on 20 January 2017 around Pedestrian Plaza
under Contract HK/2012/08, no particular observation regarding air quality
impact was observed during sampling. In view of the above, the action level
exceedance was considered to be non-project related and potentially contributed
by local ambient condition such as road traffic next to the monitoring station.
6.3.1 There was no non-compliance from the site audits in the reporting
period. The observations and recommendations made in each individual site audit
session were presented in Section 8.
6.4.1 There was no particular action taken since no non-compliance was
recorded from the site audits in the reporting period.
7.0.1. According to the Condition 3.4 of the EP-376/2009, this section
addresses the relevant cumulative construction impact due to the concurrent
activities of the current projects including the Central Reclamation Phase III
(CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass (CWB),
Island Eastern Corridor Link projects (IECL) and Wan Chai Development Phase II
– Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel).
7.0.2.
According to the Final EM&A report of Central Reclamation Phase III
(CRIII) for Contract HK 12/02, the major construction activities were completed
by end of January 2014 and no construction activities were undertaken
thereafter and the water quality monitoring was completed in October 2011. As such, it is considered that there
were no cumulative construction impact due to the concurrent activities of the
current projects with the Central Reclamation Phase III (CRIII) undertaken by
contractor HK12/02 in the reporting month.
7.0.3. According to the construction programme of Central-Wanchai Bypass at
Wanchai West at the Central Reclamation Phase III area include road works,
backfilling works and reinstatement of Culvert K were performed in January 2017
reporting month. As no project related exceedance were recorded during the
reporting period, cumulative construction impact due to the concurrent
activities of the current projects with the Central Reclamation Phase III
(CRIII) was considered as insignificant.
7.0.4.
According to the construction programme of Wan Chai Development Phase
II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, the
major construction activities under Wan Chai Development Phase II were, road
and drains, building demolition and tunnel works at Wan Chai East, tunnel
construction and backfilling works and ELS works at Wan Chai West. The major
construction activities under Central-Wan Chai Bypass and Island Eastern
Corridor Link Projects were road works and ventilation building construction at
Central Interchange, reinstatement of Eastern Breakwater, ELS works and
retaining wall construction at Victoria Park, ELS works and tunnel works at
TS3, bridge construction, piling and tunnel works at North Point area in the
reporting month. In addition, other non-Wan Chai Development Phase II,
Central-Wan Chai Bypass and Island Eastern Corridor Link projects was observed undertaken at Wan Chai North and North Point area.
7.0.5. No significant air impact from construction activities was anticipated
in the reporting month. Besides, no project related exceedance was recorded
during the water, air and noise environmental monitoring events in the
reporting month. Thus, it is evaluated that the cumulative construction impact
from the concurrent projects including Central Reclamation Phase III (CRIII),
Wan Chai Development Phase II (WDII), Central-WanChai Bypass (CWB), Island
Eastern Corridor Link projects (IECL) was insignificant.
8.0.1.
Five site inspections for Contract no.
HK/2012/08 were carried out on 28 December 2016, 3, 10, 17 and 24 January 2017 in
this reporting period. The results of
inspection and outcome are summarized in Table
8.1.
Table 8.1 Summary
of Environmental Inspections for Contract no. HK/2012/08
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
161220_01 |
20 Dec 2016 |
Contractor shall ensure the discharge at
Slip Road 1 is following the terms and condition of the wastewater discharge
licence. |
The concerned discharge was observed suspended. |
Completion as observed on 24 January 2017. |
9.0.1. No environmental complaint was received in the reporting period.
9.0.2.
The details of cumulative complaint log and
updated summary of complaints are presented in Appendix 9.1
9.0.3. Cumulative statistic on complaints and successful prosecutions are
summarized in Table 9.1 and Table 9.2 respectively.
Table 9.1 Cumulative
Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement
works (May 2015) to last reporting month |
0 |
January
2017 |
0 |
Total |
0 |
Table 9.2 Cumulative Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month
(Offence Date) |
Cumulative No. Project-to-Date |
Air |
0 |
0 |
0 |
Noise |
0 |
0 |
0 |
Water |
0 |
0 |
0 |
Waste |
0 |
0 |
0 |
Total |
0 |
0 |
0 |
10.0.1. The EM&A programme was carried out in accordance with the EM&A
Manual requirements, minor alterations to the programme proposed were made in
response to changing circumstances.
10.0.2. The scheduled construction activities and the recommended mitigation
measures for the coming month are listed in Table 10.1. The
construction programmes of individual contracts are provided in Appendix 10.1.
Table 10.1 Summary of Key Construction Activities of Individual
Contract(s) to be commenced in Coming Reporting Month
Contract No. |
Key Construction Works |
Recommended
Mitigation Measures |
HK/2012/08 |
·
Drainage |
·
Dust control during dust generating works; ·
Implementation of proper noise pollution
control; and ·
Provision of protection to ensure no
runoff out of site area or direct discharge into public drainage system. |